| Get PDF | 519308 | 2018-011809 | 2017_02_06 Spirit re-use pump station status to CDM | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519309 | 2018-011809 | 2017_02_07 Final CO Costs from Wildcat | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519310 | 2018-011809 | 2017_02_16 CO #2 reviewed by Wildcat and needs changes | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519311 | 2018-011809 | 2017_02_21 Additional CO work for floor coatings | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519312 | 2018-011809 | 2017_02_22 CO#2 sent to CDM | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519313 | 2018-011809 | 2017_02_23 CoW Re-Use Water PS - PRV | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519314 | 2018-011809 | 2017_02_24 response from Rebecca on CO #2 | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519315 | 2018-011809 | 2017_03_16 CO Clarifictions from Wilcdcat | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519316 | 2018-011809 | 2017_03_21 Air compressor moved to MCC Room | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519317 | 2018-011809 | 2017_03_21 Pump Stand and injection valves 1497.30 | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519318 | 2018-011809 | 2017_04_04 Wildcat asks if brine pump frame needs replaced | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519319 | 2018-011809 | 2017_04_06 Wildcat provides CO costs from Decker for bulk salt feeder | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519320 | 2018-011809 | 2017_04_07 Wildcat provides CO costs from Mechanical for bulk salt feeder | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519321 | 2018-011809 | 2017_04_17 MKEC evaluates Bulk salt feed CO | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |
| Get PDF | 519322 | 2018-011809 | 2017_04_27 final costs for mechanical_bulk salt feed | | 2305 E 57th St S ; Sewage Treatment Plant 2 | 468-85112 | 10/08/2018 |